SCHEDULE 5 – SoW

1.

SERVICES

The Supplier commits to assisting the Customer in implementing the Software for one (1) company within the Customer's environment by providing the following Implementation Services at the price specified in the Agreement.

  1. Start-up Meeting
    The Supplier will schedule a Start-up meeting to discuss the implementation methodology, roles, and responsibilities, align the project scope and plan with the Customer.
  2. Technical Meeting & Preparations
    The Supplier will arrange a technical meeting to guide the customer through the Software deployment process, inform the Customer about Document Integration module installation and other technical requirements, and gather technical requirements and dependencies.
  3. Standard Microsoft Dynamics Dependency Configuration Meeting
    The Supplier will inform the Customer of the required configuration in MicrosoftDynamics standard settings, to ensure the Customer’s standard D365 FO setup and configuration is compatible with the Software.
  4. Workshops
    The Supplier will arrange workshops for the Customer's implementation project team. The workshop's purpose is to review the standard Software solution, gathering information for the Software setup and identifying any potential gaps. Workshops related to additional companies will be provided at the Supplier's Consultancy Services rate specified in the Agreement.
  5. Configuration
    The Supplier will set up and configure the Software according to best practices and decisions made during the workshops. The Software will be configured in all requested non-production environments for one (1) company in one network. If the Customer requires assistance setting up additional companies, this assistance will be provided at the Supplier's Consultancy Services rate specified in the Agreement.
  6. Super User Training
    The Supplier will schedule Super User training session(s) according to the Suppliers’ implementation methodology for the Customer's employees responsible for accounts payable. Additional training, if requested, it will be provided at the Suppliers’ Consultancy Services rate specified in the Agreement.
  7. Project Management
    Project management services will be provided throughout the implementation project at the Supplier’s Consultancy Services rate specified in the Agreement. Project management is considered a Consultancy Service and is not included in the price of the Implementation Services.

2.

CUSTOMER RESPONSIBILITIES

The successful delivery of Implementation Services by the Supplier relies on the active involvement of the Customer and the Customer’s provisioning of reasonable assistance. Therefore, it is the Customer’s responsibility to:

  1. Deployment
    Ensure the deployment and activation of the Software in accordance with Microsoft standard procedures.
  2. Project Management
    Assign a project leader from within the Customer's organization responsible for example allocating resources, managing work related to the implementation of the Software, and serving as the primary point of contact for all communication with the Supplier and arranging a remote connection for the Supplier to the Customer's environment.
  3. Resources
    Ensure that an adequate number of qualified personnel from the Customer's organization are present and available throughout the implementation and testing phases.
  4. Standard D365 FO Setup, Electronic Reporting, Master and Business data
    Ensure that the Customer’s standard D365 FO Setup and Configuration are done according to agreed requirements, that it contains correct Customer’s Master & Business data and that Electronic Reporting is available.
  5. Azure Marketplace subscription
    Ensure that the Customer’s environment does have a compatible non-CSP subscription available and then buy a corresponding subscription offer.
  6. ExFlow version
    Ensure that the latest required ExFlow version is deployed.
  7. User Acceptance Testing
    Conduct thorough User Acceptance Testing (UAT) to validate the functionality and performance of the Software, ensuring alignment with the specified requirements and objectives. Promptly inform the Supplier of any defects found in the Software or its implementation during the Customer's acceptance testing.
  8. User Acceptance Sign-Off
    Upon successful completion of user acceptance testing in the Customer's test environment, the Customer shall formally accept the delivery of the Software. This acceptance shall be verified in writing, confirming that the Software has been tested and approved. Once the Software is deployed in the Customer's production environment, the Supplier considers its delivery accepted by the Customer.